Title: The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department approves the Memorandum of Agreement between MDOT, GLWA and Detroit and also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote, including the execution of the Memorandum of Agreement.
Indexes: Board of Water Commissioners

Title

The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department approves the Memorandum of Agreement between MDOT, GLWA and Detroit and also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote, including the execution of the Memorandum of Agreement.

Body

Agenda of May 18, 2022

Item No. 220814

 

TO:                       The Honorable   

                     Board of Water Commissioners  

                     City of Detroit, Michigan

 

FROM:                      Palencia Mobley, Director, Deputy Director and Chief Engineer, Detroit Water and Sewerage Department

 

RE:                     Memorandum of Agreement between MDOT, GLWA and Detroit

                     Regarding I-94 Modernization Project, Package 1 Drainage

 

MOTION

Upon the request of Deputy Director and Chief Engineer, Palencia Mobley, the Board of Water Commissioners for the City of Detroit Water and Sewerage Department (DWSD), approves the Memorandum of Agreement between MDOT, GLWA and the City of Detroit and authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote, including the execution of the Memorandum of Agreement.

 

BACKGROUND AND JUSTIFICATION


The I-94 Modernization Project (the Project) is to reconstruct approximately 6.7 miles of the I-94 mainline freeway in the City of Detroit from east of the I-96/I-94 interchange to east of the I-94/Conner Avenue interchange, approximately 1.8 miles of M-10 from Martin Luther King Jr. Boulevard to Seward Avenue including the I-94/M-10 system interchange, and the I-94/I-75 system interchange. Reconstruction includes the freeway, bridges, interchanges, service drives/local roads, stormwater drainage systems, and roadway appurtenances within the Project limits. The Project includes reconstruction of the freeway and the addition of one lane in each direction, widened shoulders to improve safety, lengthening the entrance and exit ramps to provide more time for drivers to safely enter and exit the freeway, elimination of left-hand entrance and exit ramps at the M-10 interchange, amongst other improvements.

 

These proposed improvements will enhance DWSD/GLWA’s compliance with Part 31 of the Michigan Natural Resources and Environmental Protection Act, 1994 PA 451 (Part 31) and the Federal Clean Water Act, 33 USC 1251 et seq. to the extent possible, the Project will alleviate flooding and storage flow to the Conner Sewer and reduce the overall total peak flow by 82% t the combined system. MDOT funding will be provided to advance the construction of wet weather CSO facilities and mitigation procedures, including backflow preventors. Finally, any proposed drainage tunnel may provide additional capacity for flooding relief.

 

COMMITTEE REVIEW

 

This matter is being presented directly to the Full Board.