Title
The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve Change Order No. 3 to Contract No. 6003126 (previously 6000802) with Giorgi Concrete LLC for the Repair of Pavement, Sidewalks, Driveways and Curb cuts at various locations throughout the City of Detroit (Project DWS-902). This amendment will add $2,500,000 for a total amended contract amount not-to-exceed $28,681,475 to this existing contract and extend the term by 92 days for a new expiration date of 9/30/21. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
Body
Agenda of July 21, 2021
Item No. 21-0531
Contract No.: 6003126 (previously 6000802) Project # DWS-902
Proposed Change Order No. 3
Contractor: Giorgi Cement (JV w Major Cement).
Address: 20450 Sherwood, Detroit, MI 48234
Current Contract Amount: $26,181,475
Proposed Change Order No. 3 Amount: $2,500,000
Proposed Total Amended Contract Amount: $28,681,475
Current Contract Term: 06/01/17 - 06/30/21 (4years & 1 month)
Proposed Extension: 07/01/21 - 9/30/21 (4 years & 4 months)
TO: The Honorable
Board of Water Commissioners
City of Detroit, Michigan
FROM: Gary Brown, Director
Water and Sewerage Department
RE: Proposed Change Order No. 3 to Contract 6003126 (Project# DWS-902), “Repair of Pavement, Sidewalks, Driveways and Curb cuts in various streets
at various locations throughout the City of Detroit with Giorgi Concrete LLC/Major Cement Company
MOTION
The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve Change Order No. 3 to Contract No. 6003126 (previously 6000802) with Giorgi Concrete LLC for the Repair of Pavement, Sidewalks, Driveways and Curb cuts at various locations throughout the City of Detroit (Project DWS-902). This amendment will add $2,500,000 for a total amended contract amount not-to-exceed $28,681,475 to this existing contract and extend the term by 92 days for a new expiration date of 9/30/21. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND / JUSTIFICATION
Detroit Water and Sewerage Department (DWSD) Contract No. 6003126 (Project# DWS-902) is part of DWSD’s on-going repair work program. The work consists of Repair of Pavement, Sidewalks, Driveways and Curb cuts in various streets at various locations throughout the City of Detroit trimming, removing and replacing concrete sidewalks, driveways and curbs.
In order to repair the leaks and breaks in DWSD’s water mains and sewers, repair work crews are required to open-cut street pavements, sidewalks and driveway areas to expose and repair DWSD’s lateral underground assets. The water/sewer repair contractors are responsible for repairing the leaking water mains - they are required to backfill the excavated areas and perform temporary (also called “soft”) restoration work. The subsequent permanent work (referred to as “hard restoration”)includes, but is not limited to, the removal of pavement cuts or patches, concrete pavement, high early strength no slump concrete base, remove and replacement of sidewalk, replacement of curb at various locations in the City of Detroit. At this time, DWSD has the following list of hard restoration work to be completed is per below.
FY22: $2,500,000
Work Priority - approx. locations Estimated Work: Estimated Costs
4 - Medical Facility, near school/Legal/MDOT 175 Work Orders $173,000
3 - Wayne County/central business district 376 Work Orders $382,000
2 - Impedes Traffic/Hazardous Sites 974 Work Orders $973,000
1 - Ombudsman/DONS/Director’s Office 52 Work Orders $60,000
0 - Vacant properties, demolition restorations, etc. 923 work orders $912,000
Under this contract, the repair of pavements, sidewalks, etc. will be accomplished to ensure that functionality is restored for safe use of the repaired area
PROCUREMENT METHOD
The solicitation for the original contract was advertised on Friday, February 22, 2017, on the Michigan Inter-Governmental Trade Network (MITN). 386 Solicitations were sent out via MITN. 11 Forms downloaded the bid package. Five (5) bids were received on Friday, March 24, 2017.
The lowest responsive equalized bidder, Giorgi Concrete LLC/Major Cement Company, Joint Venture has submitted all required responsive documents. Therefore, it is recommended that Giorgi Concrete LLC/Major Construction Company, Joint Venture be awarded DWSD Contract No. 6003126 (Project# DWS-902). Giorgi Concrete LLC (Joint venture with Major Construction Company) is a Detroit Based Business and will currently perform 100 percent of the work under this contract.
Change Order #1 requested to extend the contract term for an additional six (6) months, for a new expiration date of 6/30/21 at the same price, scope, terms and conditions of the initial contract.
Proposed Change Order #2: is requesting additional funds in the amount of $2,500,000, for a new total amendment amount not-to-exceed $26,181,475 at the same price, scope, terms and conditions of the original contract.
Proposed Change Order #3: is requesting additional funds in the amount of $2,500,000 for a new total amendment amount not-to-exceed $28,681,475 and for to extend the contract an additional (3) months, for a new contract expiration date of 9/30/2021 at the same price, scope, terms and conditions of the initial contract.
DWSD procurement has received the requisition to solicit for a new replacement contract and will bring that contract before the BOWC for approvals.
SUMMARY
Contract No.: 6003126 (previously 6000802) - project# DWS-902
Contractor: Giorgi Concrete JV Major Cement
Contract Amount: $26,181,475
Current Expiration Date: June 30, 2021
Funding Source I&E and O&M
GL Strings:
5721-20244-487711-617900-900203-10792-0000-000000 - 85%
5820-20178-492431-622300-000203-15826-0000-000000 - 15%
This proposed amendment was presented to the DWSD Finance Committee on July 7, 2021. Per DWSD procurement protocol, Mayoral Review and City Council approval will also be obtained.