Title
The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve Amendment No. 2 for DWSD Contract No. 6003012 (fka 6002757) with Itron, Inc. for the Water SaveSource Warranty Replacement Program - Open Way Riva AMI Implementation, by adding $522,500.00 in funding, for a total amended contract amount not-to-exceed $18,762,500.00. No changes to scope of work or the terms and conditions of this contract. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
Body
Agenda of September 4, 2024
Item No. 2024-175
Proposed Amendment No. 2
Contract No.: 6003012 (fka 6002757)
Contractor: Itron, Inc.
Address: 2111 N Molter Rd., Liberty Lake, WA 99019
Current Contract Amount: $18,240,000.00
Proposed Amendment No. 2 Amount: $522,500.00
Proposed New Total Contract Amount: $18,762,500.00
Contract Term: 12/15/11 - 12/31/99
TO: The Honorable
Board of Water Commissioners
City of Detroit, Michigan
FROM: Gary Brown, Director
Detroit Water and Sewerage Department
RE: Proposed Amendment No. 1 to Contract No. 2856616
To add funds to the contract to provide support for Open Way Riva Devices
Itron, Inc.
MOTION
Upon recommendation of Marqaicha Welch, Procurement Manager, the Board of Water Commissioners for the City of Detroit, Water and Sewerage Department, authorizes the Director to approve Amendment No. 2 for DWSD Contract No. 6003012 (fka 6002757) with Itron, Inc. for the Water Save Source Warranty Replacement Program - Open Way Riva AMI Implementation, by adding $522,500.00 in funding, for a total amended contract amount not-to-exceed $18,762,500.00. No changes to scope of work or the terms and conditions of this contract. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND & JUSTIFICATION
DWSD’s (pre-bifurcation) contract CM-2007 implemented the Itron, Inc. (Itron) fixed-base retail Automated Meter Reading (AMR) system, commercially known as Water SaveSourceTM, to automatically collect the water meter reads from DWSD’s retail customers. Beginning December 2007, the Water SaveSourceTM system began its production, which required Customers to have properly functioning meter reading equipment to maintain water service at their residence.
In March 2017, Itron notified DWSD that due to on-going changes in reading automation system technologies market it would no longer manufacture the component parts of the Water Save Source system technology, which DWSD had purchased in 2006. Further, Itron no longer had parts in inventory for modules and collector units needed to maintain the existing system for the expected and warranted 20-year useful life of the system. There was no substitute product compatible with the existing collection network and software system.
In April 2017, DWSD weighed its legal and operational options and opted to negotiate a new contract with Itron, which would take advantage of the current relationship, leverage warranty provisions of the initial Agreement and obtain the latest reading technology improvements at favorable terms.
By March 2020, DWSD and Itron reached an agreement to replace the Water SaveSource System with the OpenWay Riva system, which the Board approved April 2020, issuing a Notice to Proceed September 29, 2020.
In October 2020, Itron notified DWSD that due to additional market changes in reading automation technologies, Itron had recently made a business decision to shift its technology platform investment support away from the previously agreed to OpenWay Riva point-to-multi- point collection network technology1 to either a mesh network2 or cellular collection solution. Itron noted that it could provide the Riva, mesh network or the cellular option. DWSD investigated the mesh network and cellular option and determined that the cellular approach would provide the longest and most technologically stable solution to DWSD’s current and future reading automation needs.
Amendment No.2 is for funding to provide meter reading equipment for the continued maintenance and support of DWSD’s strategic efforts to monitor water usage and ensure the accuracy of billing.
PROCUREMENT METHOD
This contract was created pre-bifurcation. It was approved by the BOWC 11/30/2011.
Amendment 1 was presented to the BOWC and approved on 5/18/2022.
Proposed Amendment 2 was submitted through requisition 520767, which was approved by Budget on 6/6/24. This Amendment requests adding $522,500 in funding. There will be no change in scope or terms and conditions.
Itron’s clearances expire 6/13/25. A formal amended contract document has been sent to the vendor for signature.
SUMMARY
A. Contract No.: 6003012 (fka 6002757)
B. Initial Contract Amount: $18,240,000.00
C. Proposed Amendment No. 2 Amount: $522,500.00
D. Proposed New Total Contract Amount: $18,762,500.00
E. Contract Term: 12/15/11 - 12/31/99
F. Funding Source: O&M Funds
G. GL String(s):
5721.20244.487711.645220.003461.30129.0000.000000. 50% Water
5821.20243.497711.645220.003461.30129.0000.000000. 50% Sewer
H. Projected Fiscal Year (FY) Contract Expenditures:
I.
FY 24/25: $522,500.00
This proposed amendment was presented to the DWSD Finance Sub Committee on September 4, 2024. Per the DWSD Procurement Policy, and past precedence, no further approvals are required.