File #: 2023-177    Version: 1 Name:
Type: Contract Status: Passed
In control: Financial Services
On agenda: 8/16/2023 Final action: 8/16/2023
Title: The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve DWSD Contract No. 6005538 for 1,335 tons of Cold Patch Material, CP-5 Modified with Cadillac Asphalt for a total contract amount not-to-exceed $186,900.00 and a term of 1 year. The BOWC also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
Indexes: Board of Water Commissioners, Finance Committee

Title

The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve DWSD Contract No. 6005538 for 1,335 tons of Cold Patch Material, CP-5 Modified with Cadillac Asphalt for a total contract amount not-to-exceed $186,900.00 and a term of 1 year. The BOWC also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.

 

Body

Agenda of August 16, 2023

Item No.: 2023-177

Contract No.: 6005538

Contractor: Cadillac Asphalt (DBB), 670 South Dix, Detroit, MI 48217

Contract Amount: $186,900.00

Contact Term: 11/1/23-10/31/24 (1 year)

 

 

TO:                                          The Honorable

                                          Board of Water Commissioners

                                          City of Detroit, Michigan

 

FROM:                     Gary Brown, Director

                                          Water and Sewerage Department

 

RE:                                          Proposed DWSD Contract 6005538

Patch Material

Cadillac Asphalt

 

MOTION

 

Upon recommendation of Marqaicha Welch, Procurement Manager, the Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve DWSD Contract No. 6005538 for 1,335 tons of Cold Patch Material, CP-5 Modified with Cadillac Asphalt for a new contract amount not-to-exceed $186,900.00 and a term of 1 year. The BOWC also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.

 

BACKGROUND / JUSTIFICATION

 

DWSD Warehouses receive, stock, store and issue materials to various DWSD Divisions to support the Field work of our Operations Group. Patch material is essential for completion of many DWSD projects. Cold patch (specification #CP-5) is used year around to patch excavation holes on streets and sidewalks made by DWSD during repairs of water and sewer assets and similar service work orders. To support their work, DWSD’s Materials Management team maintains a readily available supply at both the CSF and West Yard warehouses. Cold patch is bid out annually due to its volatile pricing. This contract will assure that operations will run smoothly and to replenish stock preventing emergency spot buys and possible work stoppage.

 

PROCUREMENT METHOD

 

This contract was procured through a Request for Bids (RFB) #506859 and was advertised on the Michigan Inter-Governmental Trade Network (MITN) website for 22 calendar days. MITN published this opportunity to 81 companies and 10 firms downloaded the bid package. Two bids were received and Cadillac Asphalt was the lowest equalized bidder.

 

 

 

 

Bidder

Bid Total

Equalization

Equal. Credits Applied

Equalized Total

Ajax Paving

$184,230.00

None

None

   $184,230.00

Cadillac Asphalt

$186,900.00

DBB - 2%

($3,738)

   $183,162.00

                     

 

Cadillac Asphalt is a Detroit Based Business and their clearances expire on 6/12/24. A formal contract document is not required. 

 

 

 

SUMMARY

 

A.                     Contract No:                                                                                    6005538

B.                     Contract Term:                                                                                    11/1/23 - 10/31/24 (1 year)

C.                     Contract Amount:                                                               $186,900.00

D.                     Anticipated FY Spend:                                                               FY 23-24: $124,600.00

                                                                                                                              FY 24-25: $62,300.00

E.                     Funding Source:                                                                                    O&M Funds

F.                     GL String:                     5720-00000-000000-150100-000000-00000-0000-000000- 100% Water                                          

 

 

This proposed contract was presented to the BOWC Finance Subcommittee on August 2, 2023.  Per DWSD procurement protocol, no additional approvals are required.