Title
The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve Amendment No.1 for DWSD Contract 6003270 with KONE Inc., to add $111,950.00 to continue providing for preventative maintenance, service and repairs for all DWSD elevators, for a total amended not-to-exceed cost of $511,950.00. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
Body
Agenda of October 19, 2022
Item No. 22-0935
Proposed Amendment No. 1
Contract No.: 6003270
Contractor: Kone Inc., 11864 Belden Court, Livonia, MI 48150
Current Contract Amount: $400,000.00
Proposed Amendment No. 1 Amount: $111,950.00
Proposed New Total Contract Amount: $511,950.00
Contract Term: 3/1/21 - 11/30/24
TO: The Honorable
Board of Water Commissioners
City of Detroit, Michigan
FROM: Gary Brown, Director
Water and Sewerage Department
RE: Proposed Amendment No. 1 to Contract 6003270
Preventative Maintenance, Services and Repairs for DWSD Elevators
Kone Inc.
MOTION
Upon recommendation of Marqaicha Welch, Procurement Manager, the Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve Amendment No. 1 for DWSD Contract 6003270 with KONE Inc., to add $111,950.00 to continue providing preventative maintenance, service and repairs for, a total amended not-to-exceed cost of $511,950.00. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND / JUSTIFICATION
Under the proposed amendment, the additional funding will be used for repairs to the administrative elevator at CSF. The contract with Kone Inc. will continue to provide preventative maintenance, along with as-needed parts, service, and repairs for Facility Operations.
The DWSD Facility Operations Department manages the repair and maintenance for all DWSD facilities. DWSD's facilit...