Title
The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve DWSD Contract 6003373, a piggyback of CoD Contract 6003182, for as-needed electrical services for a term of 21 months, with Power Lighting & Technical Services with a total contract amount non-to-exceed $1,340,000. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
Body
Agenda of March 17, 2021
Item No. 21-0422
Contractor: Power Lighting & Technical Services (DBB & DRB)
Contractor Address: 10824 West Chicago, Suite 200, Detroit, MI 48204
CoD Contract No. 6003182
DWSD Contract No. 6003373
DWSD Amount: $1,340,000
Contract Term: 3/22/2021 - 1/18/2023 (21 months)
TO: The Honorable
Board of Water Commissioners
City of Detroit, Michigan
FROM: Gary Brown, Director
Detroit Water and Sewerage Department
RE: Proposed Contract 6003373 for as-needed electrical services for DWSD Field Services and Information Technology and an Electrical Capital Project for DWSD Facility Operations from Power Lighting & Technical Services (piggyback on CoD Contract 6003182)
MOTION
Upon recommendation of Mamata Burgi, Procurement Manager, the Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve DWSD Contract 6003373 to piggyback CoD Contract 6003182, for as-needed electrical services for a term of 21 months, with Power Lighting & Technical Services with a total contract amount non-to-exceed $1,340,000. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND / JUSTIFICATION
This proposed contract is to request to piggyback the City of Detroit Contract #6003182 for as-needed electrical services to be utilized by DWSD Field Services, IT and Facilities departments.
DWSD Field Services
Field Services is responsible for keepin...