Title
The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve Amendment No. 1 to DWSD Contract 6003967, with LGC Global, Inc., for Water Main Repairs (WS-719); by adding funding in the amount of $750,000.00, for a new amended contract amount not-to-exceed $29,688,000.00 and extending the term by 60 days for a new term expiring 1/29/2025. No changes to scope of work, or contract terms and conditions. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
Body
Agenda of November 20, 2024
Item No. 2024-228
Proposed Amendment No. 1
Contract No.: 6003967 (WS-719)
Contractor: LGC Global, Inc. (DHB, DBB)
Address: 7310 Woodward, Suite 500, Detroit, MI 48202
Current Contract Amount: $28,938,000.00
Proposed Amendment No. 1 Amount: $750,000.00
Proposed New Total Contract Amount: $29,688,000.00
Current Contract Term: 11/30/2021 - 11/29/2024 (3 years)
Proposed Amendment No. 1 Extension: 11/30/2024 - 1/29/2025 (60 days)
Proposed New Contract Term: 11/30/2021 - 1/29/2025
TO: The Honorable
Board of Water Commissioners
City of Detroit, Michigan
FROM: Gary Brown, Director
Water and Sewerage Department
RE: Proposed Amendment No. 1 to Contract 6003967 (WS-719)
Water Main Repairs (As Needed)
LGC Global, Inc.
MOTION
Upon recommendation of Marqaicha Welch, Procurement Manager, the Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve Amendment No. 1 to DWSD Contract 6003967, with LGC Global, Inc., for Water Main Repairs (WS-719); by adding funding in the amount of $750,000.00, for a new amended contract amount not-to-exceed $29,688,000.00 and extending the term by 60 days for a new term expiring 1/29/2025. No changes to scope of work, or contract terms and conditions. This also authorizes the Director to take such other action as may be necessary to accomplish the intent ...
Click here for full text