Title
The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve Amendment No. 4 to DWSD Contract 6004444 (DWS-919), with Major Contracting Group Inc., for Hard Surface Restoration Repairs; by adding 183 days and $7,000,000.00 in funding, for a total amended contract amount not-to-exceed $46,937,100.00 and a new term date ending 12/30/26. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
Body
Agenda of June 17, 2026
Item No. 2026-130
Proposed Amendment No. 4
Contract No.: 6004444 (DWS-919)
Contractor: Major Contracting Group Inc. (DBB, DHB, DSB)
Address: 15347 Dale Street, Detroit, MI 48219
Current Contract Amount: $39,937,100.00
Proposed New Total Contract Amount: $46,937,100.00 (++ $7,000,000.00)
Current Contract Term: 6/16/22 - 6/30/26
Proposed New Total Contract Term: 6/16/22 - 12/30/26 (++ 183 days)
TO: The Honorable
Board of Water Commissioners
City of Detroit, Michigan
FROM: Gary Brown, Director
Water and Sewerage Department
RE: Proposed Amendment No. 4 to DWSD Contract 6004444 (DWS-919)
To add funds to the Contract for Hard Surface Restoration Repairs
Major Contracting Group Inc.
MOTION
Upon recommendation of Marqaicha Welch, Procurement Manager, the Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve Amendment No. 4 to DWSD Contract 6004444 (DWS-919), with Major Contracting Group Inc., for Hard Surface Restoration Repairs; by adding 183 days and $7,000,000.00 in funding, for a total amended contract amount not-to-exceed $46,937,100.00 and a new term date ending 12/30/26. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
BACKGROUND / JUSTIFICATION
To repair leaks and breaks in DWSD water mains and sewers, field crews must open-cut street pavements, sidewalks, and dri...