File #: 13-0160    Version: 1 Name:
Type: Contract, Construction Status: Passed
In control: Customer Service
On agenda: 4/24/2013 Final action: 4/24/2013
Title: The Board of Water Commissioners authorizes the Director to enter into Contract No. DWS-894, "Water Shut-Off/Turn-On Project" with Homrich Wrecking, Inc. (Contractor), at a cost not-to-exceed $5,599,999.50 for a duration of 730 calendar days, and also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
Indexes: ORCAP Committee
Attachments: 1. DWS-894 BOWC Letter Second Revised 4-15-13, 2. DWS-894 Attachment
Title
The Board of Water Commissioners authorizes the Director to enter into Contract No. DWS-894, "Water Shut-Off/Turn-On Project" with Homrich Wrecking, Inc. (Contractor), at a cost not-to-exceed $5,599,999.50 for a duration of 730 calendar days, and also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.