Title
The Board of Water Commissioners authorizes the Deputy Director to enter into Contract No. PC-773D, "Consolidated Process Control System Upgrades for Wastewater System", with Emerson Process Management, at a cost not-to-exceed $3,364,834.45 for a duration of 1,095 calendar days, and also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.