Detroit Water and Sewerage Department
File #: 19-00198    Version: 1 Name:
Type: Contract Status: Passed
In control: Board of Water Commissioners
On agenda: 7/12/2019 Final action: 7/12/2019
Title: The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to enter into Contract No. 6002230 for "Water Improvements for Cornerstone Village (WS-712)" with Ric-Man Construction, Inc., at a cost not to exceed $18,630,333.50 for a duration of two (2) years, and also authorizes the Director to take such action necessary to accomplish the intent of this vote.
Indexes: Finance Committee

Title

The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to enter into Contract No. 6002230 for "Water Improvements for Cornerstone Village (WS-712)” with Ric-Man Construction, Inc., at a cost not to exceed $18,630,333.50 for a duration of two (2) years, and also authorizes the Director to take such action necessary to accomplish the intent of this vote.

 

Body

Agenda of July 12, 2019

Item No. 19-00198

Proposed Contract No. 6002230

Contractor:                      Ric-Man Construction, Inc.

                                          7310 Woodward Avenue, Suite 500

                               Sterling Heights, MI  48314

Contract Amount:  $18,630,333.50

Contract Term:  Two (2) years (730 days)

                                               Anticipated Dates:  9/1/19 - 8/31/21

 

 

TO:                                          The Honorable

                                          Board of Water Commissioners

                                          City of Detroit, Michigan

 

FROM:                      Gary Brown, Director

                                          Water and Sewerage Department

 

RE:                     Proposed DWSD Contract No. 6002230

"Water Improvements for Cornerstone Village (WS-712)”

 

 

MOTION

 

Upon recommendation of Palencia Mobley, Deputy Director/Chief Engineer, the Board of Water Commissioners for the City of Detroit Water and Sewerage Department authorizes the Director to enter into Contract No. 6002230 for "Water Improvements for Cornerstone Village (WS-712)” with Ric-Man Construction, Inc., at a cost not to exceed $18,630,333.50 for a duration of two (2) years, and also authorizes the Director to take such action necessary to accomplish the intent of this vote.

 

 

BACKGROUND

 

Proposed DWSD Contract No. 6002230 (WS-712) is part of an ongoing distribution piping system water main replacement program and is the result of extensive condition assessment work completed under Contract No. 6000777 (CS-1812).  The work consists of either replacing or lining over 46,000 linear feet of existing 6-inch, 8-inch, 12-inch, and 16-inch water mains that have a history of frequent breaks and high maintenance cost.  The work also includes replacement of attendant gate valves and fire hydrants.  The aggregate forecasted length of Lead services being replaced with copper within the public right-of-way (ROW) in Cornerstone Village is 20,000 linear feet and 19,800 linear feet on private properties.  For this project, lead services replacement costs account for approximately six percent of the contractor’s bid.  Finally, lead services of one inch and less in diameter are replaced with one-inch copper tube; existing lead services of 1.5-inches and 2-inches diameter are replaced with copper tube of the same diameter. 

 

JUSTIFICATION

 

This water main replacement contract is one of a continuing series of contracts that replaces or lines the aged water mains in the City of Detroit having an extensive history of leaks and breaks that have exceeded their intended service life.  The new water mains and associated infrastructure will enhance the integrity of DWSD’s Water System and ensure quality service to its customers.  To protect the health and safety of our customers, existing lead water services are being replaced with copper in both the right-of-way and from curb box to the customer water meter.

 

The water main replacement work is broken down as follows:

 Street

 From

 To

New Ductile Iron Water Main (Linear Feet)

 

 

 

8-Inch

12-Inch

16-Inch

Moross

Edsel Ford

Alstead

145

 

 

Alstead

Moross

Kingsville

500

 

 

Canyon

Edsel Ford

Rockcastle

455

 

 

Canyon

Mallina

Berden

378

 

 

Berden

Canyon

Moross

378

 

 

Hillcrest

Rolandale

Mack

2790

 

 

Chandler Park

Gateshead

Lannoo

624

 

 

Chandler Park

Lannoo

Moross

565

 

 

Rolandale

Canyon

Moross

500

 

 

Lannoo

Canyon

Linville

596

 

 

Lannoo

Linville

Chandler Park

665

 

 

Canyon

Canyon

Balduck Park

56

 

 

Warren

Warren

Balduck Park

90

 

 

Canyon

Opal

Warren

551

 

 

Canyon

Warren

Mack

500

 

 

Radnor

Frankfort

Mark

2520

 

 

Warren (north)

Farmbrook

Canyon

1325

 

 

Warren (south)

Farmbrook

Canyon

 

1375

 

Farmbrook

Edsel Ford

Chandler Park

3380

 

 

Radnor

Chester

Chandler Park

2557

 

 

Chester

Chester

Marseilles

31

 

 

Chester

Marseilles

Canyon

 

836

 

Chandler Park

Lodewyck

Radnor

524

 

 

Farmbrook

Chandler Park

Cornwall

2675

 

 

Hereford

Minerva

Chandler Park

1548

 

 

Mack

Neff

Hereford

599

 

 

Chester

Chester

Neff

125

 

 

Harper

Harper

Chester

 

24

 

Harper

Harper

Chester

 

 

126

 

 

WarrenCadieuxGuilford770

 

 

 

 

 

Guilford

Alley

Warren

131

 

 

Woodhall

Chandler Park

Southampton

729

 

 

Warren (north)

Guilford

Woodhall

681

 

 

Warren (north)

Guilford

Woodhall

 

17

 

Guilford

Harper

Chandler Park

2974

 

 

Cadieux

Cadieux

Chandler Park

 

165

 

Chandler Park

Cadieux

Bluehill

501

 

 

Bluehill

Chandler Park

Southampton

707

 

 

Oldtown

Chandler Park

Southampton

635

 

 

Southampton

Oldtown

Bluehill

288

 

 

New York

Cadieux

Guilford

825

 

 

Sioux

Cadieux

Guilford

868

 

 

Cincinnati

Cadieux

End of Street

649

 

 

Waveney

Cadieux

Guilford

641

 

 

Detroit

Cadieux

Guilford

651

 

 

Mack

Moross

Allard

 

4

640

Rolandale

Rolandale

Kingsville

60

 

 

Linville

Moross

Kingsville

52

 

 

Lafontaine

Canyon

Mack

71

 

 

Anatole

Canyon

Mack

90

 

 

Opal

Canyon

Mack

67

 

 

Radnor

Chandler Park

Southampton

67

 

 

University

Munich

Mack

45

 

 

Cadieux

Warren

New York

 

12

 

 

 

Total:

34809

3203

766

 

 

 

 

 

 

 

 

 

Lining of Existing Water Mains

 

 

 

8-Inch

12-Inch

16-Inch

Roldandale

Moross

Kingsville

465

 

 

Linville

Moross

Kingsville

491

 

 

Lafontaine

Canyon

Mack

1333

 

 

Anatole

Canyon

Warren

963

 

 

Opal

Canyon

Mack

559

 

 

Radnor

Chandler Park

Frankfort

1137

 

 

University

Munich

Mack

1336

 

 

Warren

Cadieux

Guilford

735

 

 

Cadieux

Warren

New York

 

372

 

 

 

Total:

7019

372

 

Project Total Piping:

46,169 Linear Feet

 

DWSD and CIPMO hosted community meetings in the Cornerstone Village in October 2018 and January 2019.  The goal of the meetings was to foster meaningful discussions about the capital improvement projects scheduled in the neighborhood. These meetings were well received by attendees and were attended by residents, business owners and notable stakeholders such as State Representative Tenisha Yancey, State Representative Joe Tate, and Councilman Andre Spivey’s Chief of Staff, Keith Jones.

 

The meeting in October 2018 focused on Green Stormwater Infrastructure improvement and the meeting in January 2019 provided a project overview of water main and sewer pipeline improvements, review of green stormwater infrastructure projects, and the process for lead service line replacements. Attendees at both meetings had the opportunity to ask questions and express concerns about the project. 

 

 

PROCUREMENT METHOD

 

This project was competitively solicited as a Request For Bids (RFB) and advertised on Wednesday, February 13, 2019, on the Michigan Inter-Governmental Trade Network (MITN) website. Notices were sent to 1,930 firms via MITN with 153 firms downloaded the bid package.  It was also advertised with the North America Procurement Council, Michigan Minority Contractors Association (MMCA), National Association of Minority Consulting Engineers (NAMCE), Asian Pacific American Chamber of Commerce (APACC), Michigan Hispanic Chamber of Commerce (MHCC), Michigan Black Chamber of Commerce (MBCC), Washtenaw Contractors Association Plan Room, Booker T. Washington Business Association, Michigan Minority Business Development Council, Construction Association of Michigan, Construct Connect,  Dodge Data & Analytics, Construction Journal,  Builders Exchange of Michigan and Bid Ocean.  Eight (8) bulletins were issued during the course of this bid. 

 

The bids were downloaded from MITN and opened on Wednesday, March 20, 2019. 

 

The engineer’s estimate for this contract was $21,351,000.00. 

 

The following five (5) bids were received:

 

Bidder

Ric-Man Construction, Inc.

Blaze Contracting Inc.

Lakeshore Global Corporation

Major Cement Co.

L. D’Agostini and Sons, Inc.

Bid Price

$18,630,333.50

$18,927,639.75

$19,990,667.35

$20,963,750.60

$20,844,321.21

Equalization(s)

None

None

None

None

None

Percentage Applied

0%

0%

0%

1%

0%

Equalization

$0.00

$0.00

$ 0.00

$209,637.51

$0.00

Equalized Bid Amount

$18,630,333.50

$18,927,639.75

$19,990,667.35

$ 20,754,113.09

$20,844,321.21

 

Although Lakeshore Global Corporation and Blaze Contracting, Inc. are both located in Detroit, the Detroit Based Business certificates submitted had expired prior to the bid deadline; therefore, they were not awarded equalization credits as part of the evaluation.

 

Ric-Man Construction, Inc., as the apparent equalized low bidder, was evaluated and determined to be responsive. 

 

 

DETAILS

 

A.                     Contract No.:                                                                6002230

 

B.                     Contract Description:                                          Water Improvements for Cornerstone Village

 

C.                      Contractor:                                                               Ric-Man Construction, Inc.

 

D.                     Contract Term:                                                               Two (2) Years (730 days)

                                                                                                                              Anticipated Dates:  9/1/19 - 8/31/21

 

E.                     Contract Amount:                                          $18,630,333.50

 

Bid Subtotal                                                                        $ 16,407,333.50

Permit Allowance                                                               $      203,000.00

Contaminated Material Allowance                                     $        20,000.00

Provisional Allowance for Unforeseen Conditions            $   2,000,000.00

Total Contract Amount:                                                   $ 18,630,333.50 

 

 

F.                     Funding Source:                                          CIP

 

G.                     GL String:                       

                            5721-20244-487711-617900-900298-30129-0000-000000 - 100%

 

H.     Projected Fiscal Year (FY) Contract Expenditures:

                     FY 20        $6,500,000.00

                     FY 21        $9,000,000.00

                     FY 22        $3,130,333.50

                                          

Proposed Contract No. 6002230 for the Water Improvements for Cornerstone Village (WS-712) project was presented to the Finance Committee on July 9, 2019.  Per DWSD procurement policy, this will also be presented to City Council after BOWC approval.