Title: The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve DWSD Contract 6004358 with Major Contracting Group, Inc. for Water System Improvements - Evergreen, Grand River, Warrendale and Franklin Park (Project WS-720), for a total contract amount not-to-exceed $13,446,362 and a term of two (2) years. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
Indexes: Board of Water Commissioners, Finance Committee
Attachments: 1. WS-720 Appendix Attachment kf
Title
The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve DWSD Contract 6004358 with Major Contracting Group, Inc. for Water System Improvements - Evergreen, Grand River, Warrendale and Franklin Park (Project WS-720), for a total contract amount not-to-exceed $13,446,362 and a term of two (2) years. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.

Body
Agenda of May 18, 2022
Item No. 22-0792
Contract No. 6004358 (WS-720)
Contractor: Major Contracting Group, Inc. (DBB), 15430 Dale, Detroit, MI 48223
Contract Amount: $13,446,362
Contract Term: 730 calendar days (2 years) - Anticipated Start Date of 7/31/22

TO: The Honorable
Board of Water Commissioners
City of Detroit, Michigan

FROM: Gary Brown, Director
Water and Sewerage Department

RE: Proposed DWSD Contract No. 6004358 / Project No. WS-720
Water System Improvements - Evergreen, Grand River, Warrendale and Franklin Park
Major Contracting Group, Inc.


MOTION

Upon recommendation of Marqaicha Welch, Procurement Manager, the Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to approve DWSD Contract 6004358 with Major Contracting Group, Inc. for Water System Improvements - Evergreen, Grand River, Warrendale and Franklin Park (Project WS-720), for a total contract amount not-to-exceed $13,446,362 and a term of two (2) years. This also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.


BACKGROUND / JUSTIFICATION

DWSD Project No. WS-720 is part of an ongoing distribution piping system water main replacement program. The work consists of replacing and rehabilitating existing piping (per Appendix A) by trenching, pipe bursting and directional drilling. Existing water mains of 6-inch, 8-inch, and 12-inch diameter water mains will be replaced at...

Click here for full text