Detroit Water and Sewerage Department
File #: 18-0079    Version: 1 Name:
Type: Procurement, Goods and Services Status: Passed
In control: Board of Water Commissioners
On agenda: 4/18/2018 Final action: 4/18/2018
Title: The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to secure a one-time purchase of new HVAC roof-top units and the related installation services from Johnson Control Inc. for a total amount of $419,933.00 and also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.
Indexes: Board of Water Commissioners
Title
The Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to secure a one-time purchase of new HVAC roof-top units and the related installation services from Johnson Control Inc. for a total amount of $419,933.00 and also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.


Body
Agenda: April 18, 2018
Item No. 18-0079
Purchase Order No. 3022335
Amount: $419,933.00


TO: The Honorable
Board of Water Commissioners
City of Detroit, Michigan

FROM: Gary Brown, Director
Water and Sewerage Department

RE: Proposed DWSD One-Time Purchase PO# 3022335
"HVAC (Roof-Top Units)"


MOTION

Upon recommendation of Thomas Naughton, CFO, the Board of Water Commissioners for the City of Detroit, Water and Sewerage Department authorizes the Director to secure a one-time purchase with Johnson Control Inc. (JCI) for HVAC Roof-Top Units for a total amount not to exceed $419,933.00 and also authorizes the Director to take such other action as may be necessary to accomplish the intent of this vote.

BACKGROUND and JUSTIFICATION

The CSF facility has been awaiting replacement parts and updates to its HVAC system, roof, lighting systems, etc. for a few years now. The serial numbers on current units indicate an approximate age of 23 years - far exceeding the roof-top-units' operational life expectancy. The evaluation also noted that "the units appear to be in a serious state of deterioration".

Due to these very old and inoperable heating, ventilation and cooling units currently on the roof of the building, certain key areas of the facility such as the central warehouse, drainage team's area and carpenter's shop are very cold in the winter and extremely hot in summer - this has caused unsafe working conditions in both winter & summer due to extreme temperatures.

This one time purchase will serve to ensure that DWSD Central Service facility is returned to...